Barbican Estate Residential Baggage Store/Storage Space Installation - Gateway 3/4 - Options Appraisal (Regular)

Report of the Director of Community and Children’s Services.

This report was approved by the Projects Sub Committee on 23rd November 2016.

Minutes:

The Committee considered a report of the Director of Community and Children’s Services in respect of the installation of baggage/storage spaces on the Barbican Estate.  Members noted that the Projects Sub Committee had approved this report on 23rd November 2016.  Members noted that, whilst unlikely to vary greatly from those in the report, exact numbers were still being worked on and more detail would emerge in the next project ‘Gateway 5’ report.

 

RESOLVED, that:

 

1.     Option 1, as set out in the report, be approved for proceeding to procurement and Gateway 5.

 

2.     The estimated budget of £618,850 be noted.

 

3.     A budget of £18,850 be approved in order to reach the next Gateway.

 

4.     An increase in staff costs of £18,850 be approved.

 