Agenda item

Guildhall - Great Hall Level Access

Report of the City Surveyor.

 

NB: This report has been considered by the Projects and the Corporate Asset Sub-Committees.

Minutes:

The Committee considered an outcome report (Gateway 7) of the City Surveyor concerning the Guildhall, Great Hall Level Access project.

 

In answer to a question about the length of time it had taken to evaluate the project, the City Surveyor advised that in future all project reviews would be completed within three months of the completion of a project.

 

RESOLVED – that the lessons learned be noted and the project be closed.