Gateway 3/4 - Crescent House/Cullum Welch House Heating Replacement

Report of the Director of Community and Children’s Services.

Minutes:

Members considered a Gateway 3/4 report of the Director of Community and Children’s Services regarding Crescent House/Cullum Welch House Heating Replacement.

 

RESOLVED, that Members

 

·         Note the contents of the report and approve Option 2 (Communal Heating).

 

·         Note the total estimated cost of £3,146,321 (including expenditure to date).

 

·         Note expenditure to date of £18,207 (plus VAT).

 

·         Approve the additional budget of £132,000 to reach Gateway 5.

 

·         Note the costed risk of £215,000 – this figure not being included in the total estimated cost but being intended as contingency and only drawn down if required.