Gateway 2 - Barbican Art Gallery Chiller Replacement

Report of the Managing Director, Barbican Centre.

 

To be read in conjunction with the Non-Public appendices found at agenda item 18.

 

 

Minutes:

Members considered a Gateway 2 report of the Managing Director, Barbican Centre regarding Barbican Art Gallery Chiller Replacement, noting the non-public appendix at Item 18.

 

RESOLVED, that Members

 

·         Approve a budget of £14,000 to reach Gateway 3/4 (staff costs, consultant fees and surveys).

 

·         Note the estimated cost range of £300,000 (excluding risk).

 

·         Approve a costed risk provision of £4,000 to be drawn down via delegation to Chief Officer.