The Sub Committee considered a report of the Director of Community and Children’s Services concerning a project for whole building refurbishment of George Elliston and Eric Wilkins Houses. The Director of Community and Children’s Services introduced the report and drew Members’ attention to the key points, also confirming that the project was fully funded via Housing Revenue Account (HRA).

 

RESOLVED – That the Projects Sub Committee:

 

  1. Agree that a budget of £200,000 is approved to cover fees and staff costs to reach the next Gateway (£150,000 for consultant fees and £50,000 for staff costs);

 

  1. Note the total estimated cost of the project at £3,706,200 (excluding risk); and

 

  1. Note that no Costed Risk Provision is required and to note the risk register appended to the report.