Gateway 2 - Smithfield Market Car Park - Sprinkler and fire door remedial works

Report of the City Surveyor

Minutes:

The Sub Committee considered a Gateway 2 report of the Director of the Built Environment regarding a project to carry out essential fire door and sprinkler head replacement at Smithfield Market Car Park.

 

RESOLVED – That the Projects Sub Committee:

 

1.    Agree that a budget of £20,000 is approved to carry out detailed surveys to reach the next Gateway;

 

2.    Note the total estimated cost of the project of £120,000 (excluding risk);

 

3.    Note that there is a Costed Risk of £30,000 (post mitigation);

 

4.    Note that the total estimated cost of the project of £150,000 (including risk); and

 

5.    Note that ‘in principle’ central funding from City Cash reserves was agreed as part of the 2020/21 annual capital bids.