Gateway 2 - Barbican Fire Door Replacement Programme

Report of the Director of Community and Children’s Services

Minutes:

The Sub Committee considered a Gateway 2 report of the Director of Community and Children’s Services regarding the Barbican Fire Door Replacement Programme.

 

RESOLVED – That the Projects Sub Committee note the report and:

 

1.    Agree that a budget of £275,000 is approved for internal staff costs and professional fees to reach the next Gateway;

 

2.    Note the total estimated cost of the project at £20,000,000(excluding risk); and

 

3.    Note the Risk Register as set out in the report.