Gateway 3/4 Issue - Fire Compartmentation - Great Arthur House

Report of the Director of Community & Children's Services

Minutes:

The Sub Committee considered a Gateway 3/4 Issue report of the Director of Community and Children’s Services regarding the fire compartmentation project at Great Arthur House. The Director of Community and Children’s Services introduced the report and drew Members’ attention to the key points.

 

RESOLVED, that:

 

1.    That £101,665 is approved to cover the remainder of Studio Partington’s design fees;

 

2.    That an additional budget of £10,000 is approved to cover the Communications Consultant’s fees;

 

3.    Additional Costs are added for staff time (£20,000); and

 

4.    Note the revised project budget of £2,050,665 (excluding risk);

 

Item

Cost (£)

Works

£1,856,000

Consultancy (Design Team)

£147,665

Consultancy (Communications)

£10,000

Staff Costs

£37,000

Total (excl. spend to date)

£2,050,665

 