Report of the City Surveyor.
Minutes:
The Chamberlain reported on the EV charge points for transition to a zero-emission fleet.
RESOLVED – That
(a) progression to Gateway 4a be approved;
(b) a £5,000 budget to proceed to the next gateway (internal staff costs) be authorised;
(c) the £157,500 total estimated cost of the project be noted; and
(d) the installation of electric vehicle (EV) charging points at key corporate facilities be supported to enable departments to implement the new zero emission fleet targets.