Agenda item

Gateway 4 Issue - West Smithfield and Charterhouse Street (Thameslink) Bridges Remedial Works

Report of the Director of the Built Environment.

Minutes:

Members considered a Gateway 4 Issue report of the Director of the Built Environment regarding West Smithfield and Charterhouse Street (Thameslink) Bridges Remedial Works. In response to a question, the Director of the Built Environment confirmed that the City’s works were insured.

 

RESOLVED, that Members

 

·     agree proposals to include additional waterproofing and re-surfacing of Charterhouse Street Bridge over Railtrack Sidings (Structure No. 33/23) as per the plan in Appendix 2, which is an increase in the scope of similar work.

 

·     agree a project budget increase of £160,000 for the increase in scope to a total of £844,000.            The increase of £160,00 is to be funded from the Additional Capital Funds for City Fund Properties Programme.

 

·     Approve a Cost Risk Provision of £70,000 over and above the £160,000 (to be drawn down via delegation to Chief Officer).

 