Gateway 2 - PAVA installation & door lock upgrade

Report of the City Surveyor.

Minutes:

Members considered a Gateway 2 report of the City Surveyor regarding PAVA Installation and Door Lock Upgrade and the following points were made.

 

·         In response to a request, the City Surveyor agreed to clarify outside of the meeting whether the project formed part of the Secure City Programme.

 

RESOLVED, that Members,

 

·         Approve a budget of £88,000 to start the upgrade doors work phase of the project.

 

·         Approve a budget of £30,000 for the PAVA project for the technical survey to progress to Gateway 3/4 via the regular approval track.

 

·         Note the project budget of £118,000 at this gateway

 

·         Note the total upper range cost of the project at £1,500,000 including risk

 

·         Note the risk register.

 

 