Outcome Report - Paul's Walk Western End

Minutes:

The Sub Committee considered a report of the Director of the Built Environment, which sought to close the Paul’s Walk Western End project.   The Director of the Built Environment and the Chairman commended Clarisse Tavin for her excellent work on this project, which had included extensive negotiations with Network Rail. 

 

However, members were concerned about the behaviour of cyclists in this area and asked if there were any plans for calming measures.  The Police representative advised that cyclists were stopped and ticketed, being encouraged to attend awareness raising courses.  The Chairman asked if means to reduce cycling on the Riverside Walk be reported to the next meeting.

 

RESOLVED, that:

 

1.     The project be closed.

 

2.     The additional staff costs of £2,503 be met from the works and fees underspend on the project.

 