Agenda item

Globe View Walkway - Opening up and Enhancing the Riverside Walk

Report of the Director of the Built Environment.

Minutes:

Jeremy Simons re-joined the meeting and resumed the Chair.

 

The Sub Committee considered the report of the Director of the Built Environment in relation to the proposals for the opening up and enhancing of a section of the Riverside Walk under Globe View.

 

The Sub Committee noted the additional fees required were to enable the architect to work on a design solution and carry out further structural investigation.

 

RESOLVED That a budget increase of £48,500 (made up of £28,500 staff costs and £20,000 fees) funded from the Watermark Place Section 106 obligation and TfL LIP programme, be approved to cover additional fees, structural surveys, and consultation to progress the project to Gateway 4.

Supporting documents: