Agenda item

Mitigation of CR11 - Hampstead Heath Ponds Project - risk update

Report of the Director of the Built Environment.

Minutes:

The Committee received a report of the Director of the Built Environment that updated Members on the mitigation of Corporate Risk 11 in relation to the Ponds Project.

 

Members were advised that the Heath and Hampstead Society had applied for judicial review; the timetable was still to be confirmed but it was hoped that the hearing might be heard in November 2014. Members noted that the planning application to the London Borough of Camden was submitted on 4 July 2014 and that project work should commence on site at Hampstead Heath in early 2015, subject to the outcome of the judicial review and planning permission being obtained.

 

RESOLVED – That the report be noted.

 