Report of the Director of Operations & Buildings.
Minutes:
The Committee considered a report of the Managing Director providing the lessons learnt from a project to migrate plant to a new Building Energy Management System, and recommending the project’s closure.
In response to a query, the Head of Projects advised that the Centre’s failure to install data points in a timely fashion ahead of the works’ scheduled start had been due to a communications gap, caused by the departure of a member of staff. It was noted that appropriate plans should be put in place to mitigate against this risk in future.
RESOLVED: that the lessons learnt be noted and, following processing of the final contractors payment, the project be closed.