The Sub Committee considered a report of the Director of the Built Environment regarding phase 1 of the Fleet Buildings and Plumtree Court public realm enhancements.
RESOLVED – That,
a) the budget setup and implementation of the 1 New Street Square highway works totalling £575,760 (fully funded by the developer), as outlined in paragraph 3 and Appendix 1 of the main report be authorised;
b) authority be delegated to the Director of the Built Environment to adjust the budget between the 1 New Street Square project elements (works, fees and staff costs) as required to meet the project needs;
c) the £216,000 budget for the Public Realm and Security Improvements (S278) scheme for the London Development to reach the next Gateway be approved;
d) the project be renamed from “Fleet Buildings and Plumtree Court” to
“Shoe Lane Quarter Public Realm Enhancements”; and
e) the outline phasing for the project, as detailed in the report which
reflected the emergence of forthcoming developments in the Shoe Lane
Quarter be noted.