Gateway 7 Outcome Report - Bury Court S278

Minutes:

The Sub Committee received a report regarding the completion of the improvement works at Bury Court where S278 funding had been provided in association with the new development at 6 Bevis Marks.

 

Although the time taken to complete the project had been slow, it had come in under the expected budget by about 30% and the contingency was also not needed.

 

Members questioned the proposal that the unspent funds be returned to the developer and suggested that instead the developer be asked if the money could be spent on further improvements in the area.

 

RESOLVED that,

 

a)        the final cost of the project be noted;

b)        that the developer be asked if the unspent funds can be put towards further improvements in the area; and

c)         the lessons learnt be noted and the project be closed.

 

 