Parking and Enforcement Plan Stage 3 - City Wide Review of Loading Restrictions and Functional Street Enhancement Project.

Minutes:

 

The Sub-Committee received a report concerning the city wide review of loading restrictions and functional street enhancing project which had now been completed.

 

In response to a question concerning how the lessons learnt were carried forward, Members were advised that officers met regularly with key stakeholders to discuss issues, and the lessons learnt were shared with internal colleagues through team meetings.

 

In response to a further question concerning whether or not there was a central co-ordination point for the lessons learnt, the Town Clerk undertook to look into this and report back.

 

RESOLVED  that,

 

a)            the lessons learnt are noted and the project closed; 

b)            the unspent funds of £26,838 be released back to the On Street Parking Account;

c)            A budget adjustment be undertaken to utilise works funding for an overspend of £10,575 on P&T staff costs;

d)            An off-street parking charges review be progressed independent of this project.

 

.