The Sub-Committee received a report of the Director of Built Environment proposing an update to the Eastern City Cluster Strategy in light of the significant developments in the area. There was a discussion on the need for developers to take responsibility for coordinating their developments, both in planning and during construction (servicing, deliveries etc.) This also needed to be reflected in improved coordination between departments within the corporation.

 

RESOLVED – That the review and update of the area strategy be authorised at an estimated cost of £160,000, funded from the Pinnacle section 106 Agreement (£100,000) and Transport for London LIP (local Improvement Plan) funding for 2016/17 (£60,000)

 