Transportation and Public Realm Division Projects Programme

Minutes:

The Sub-Committee received a report of the Director of the Built Environment setting out the programme for the current and upcoming (Gateway 2) Transportation and Public Realm projects. Of the £164 million cost of the works £3.8 million had been contributed from the Corporation budget. There was a discussion on the scope of the Bus reliability project; officers confirmed that this had been developed under a directive from TfL. The use of finger posts for way-finding was also discussed and it was confirmed that way-finding review would be linked to the development of the Cultural hub

 

RECEIVED

 