1 Angel Court Improvements GW4-5 V9

Minutes:

The Sub-Committee considered a report of the Director of Built Environment detailing the works to the Angel Court area, due to commence in October-November 2016, with completion set for March 2017. In response to a query from Members it was confirmed that the proposed seating would include anti-skateboarding grooves. Members asked if the height of the benches could be raised, both to improve the comfort for less mobile users and to further deter skateboarding. Officers undertook to investigate the proposal.

 

RESOLVED – That the design as shown in Appendix 3 of the report and the implementation of the project at a total estimated cost of £333, 061 be approved, with works to be undertaken by the City’s highway term contractor, JB Riney.

 