Eastern City Cluster - Public Art (Year 6 & 7-9)

Report of the Director of the Built Environment.

 

This report has been considered by the Culture, Heritage and Libraries Committee, the Streets and Walkways Sub Committee and the Projects Sub Committee.

Minutes:

Members considered a report of the Director of the Built Environment regarding Eastern City Cluster Public Art.

 

RESOLVED, that Members

 

·         Note the contents of the update report;

·         Agree to retain the project in-house for the next three years;

·         Agree that any underspend from previous years is transferred to future years of the project;

·         Approve the appointment and/or procurement of all services associated with the delivery of the project for years 2017-19 in accordance with Section 5 of this report;

·         Delegate authority to the Director of Transportation and Public Realm and Head of Finance to adjust the project budget between staff costs, fees and works (and between Years 7-9), providing the overall budget is not exceeded;

·         Approve a contribution of £360k from the S106 obligation connected with the Pinnacle development at 22 Bishopsgate towards the implementation of the next 3 years of the project.   