Agenda item

Gateway 7 Outcome Report: Replacement of lighting, small power and distribution boards

Report of the Chief Operating & Financial Officer.

Minutes:

The Committee considered a report of the Chief Operating & Financial Officer concerning a project to replace lighting, small power and distribution boards in various locations across the Centre.

 

In response to a query concerning the nature of the project delays, the Head of Projects advised that the project’s initial rejection by the Projects Sub-Committee and the subsequent change in scope needed to gain approval had required the start of works to be delayed. Consequently, the delivery window had slipped and had then needed to be altered further to avoid clashes with pre-planned events at the Centre.

 

RESOLVED: That the lessons learnt be noted and, following the end of the defects liability period and payment of any retention, the project be closed.

 

Supporting documents: