Minutes:
The Sub-Committee received a report relating to the redevelopment of 60-70 St Mary Axe, and the associated changes that would be required as set out in the accompanying Section 106 agreement.
The Sub-Committee was advised that once options had been drafted a wider public consultation would be arranged to ensure that stakeholders in the wider area were given an opportunity to consider and comment on the proposals.
In response to a question concerning assurance that there would be built in resilience arrangements, officers advised that this would be a key focus of the traffic assessments and would also be funded by the Section 106 funding. A further paper on an electrical charging policy would also be coming to the Sub-Committee.
RESOLVED – To approve the Scheme Objectives as detailed in Appendix 1 of the report and authorise the progression of the project and the release of funds as set out in Table 2 – subject to the receipt of funds.
Supporting documents: