Members received a Gateway 6 report concerning the Lime Street and Cullum Street area project.
RESOLVED – To
1) Approve the revised design for Lime Street as shown in Appendix 1;
2) Approve authority to start work following completion of the construction information at a total project cost of £526,331 as set out in appendix 2.
3) Approve the revised total project sum of £824,929 (inclusive of Lime Street area project, Lime Street Traffic Management Experiment and Cullum Street);
4) Approve the additional funding required of £248,323 and that it be met from the underspend of the completed Cullum Street (£63,926) and Lime Street Traffic Experiment (£3,532) projects and £180,865 from the Section 106 contribution connected to 20 Fenchurch Street (specific in purpose and geography).