The Sub-Committee received a Report of the City Surveyor concerning the bridges at West Smithfield and Charterhouse Street.

 

RESOLVED – that the Sub-Committee approved the following:

 

·         Option 2 from the Options Appraisal Table is approved (i.e. full programme of

works identified to both bridges)

 

·         The project budget of £684,000 is approved (inclusive of £100,000 risk allowance)

 

·         Currently approved Cyclical Works Programme (CWP) funding of £230,000 is

transferred to this project and managed under the Gateway project procedures

 

·         Additional funding of £323,000 from the Additional Capital Funds for City Fund

Properties Programme (as approved by RASC 18th January 2018) is allocated

to the project & managed under the Gateway project procedures

 

·         Additional funding of £131,000 from savings in the 2016/17 Additional Works

Programme (AWP) is allocated to the project and managed under the Gateway project procedures

 

 

 