Agenda item

City Cycleways Programme (Phases 1, 2 and 3)

Report of the Director of the Built Environment

Minutes:

The Sub-Committee considered a report of the Director of the Built Environment seeking approval for delivery of a programme of pedal cycle projects as proposed in the City’s adopted Transport Strategy (May 2019). Members stressed the value of minimal physical segregation to avoid further limiting road space.

 

RESOLVED – That the Streets & Walkways Sub-Committee:

 

1.    Approve the first three phases of the Cycleways Programme as described in the report;

 

2.    Approve a budget of £450,000 to reach the next Gateway; and

 

3.    Note the total estimated cost of the three phases is in the region of £3.5M - £4.5M (excluding risk).