Tower Bridge HV System Replacement and Increasing Resilience

Report of the City Surveyor.

 

N.B: - To be considered alongside a Non-Public Appendix at Agenda Item 18

Minutes:

The Committee considered a report of the City Surveyor concerning the electrical infrastructure at Tower Bridge.

 

RESOLVED – That the Planning & Transportation Committee agree:

 

1.    That approval is obtained to proceed straight to Detailed Design stage (G4c). The G4c will be approved by the Planning & Transportation and Project Subs committee Members;

 

2.    That additional budget of £431,095 is approved for professional fees required between Gateway 4 and Gateway 4c and for the first payment to UKPN for the installation of the new HV intake;

 

3.    Note the revised approved budget will be £760,155 (excluding risk);

 

4.    That a Costed Risk Provision of £355,000 is approved for Gateway 4 to Gateway 4c; and

 

5.    That approval of Gateway 4c and Gateway 5 is delegated to the Planning & Transportation and Project Sub Committee Members.