Fleet Street and Temple Healthy Streets Plan

Report of the Director of the Built Environment

Minutes:

The Sub Committee considered a report of the Director of the Built Environment regarding the Fleet Street and Temple Healthy Streets Plan. The Director of the Built Environment introduced the report and drew Members’ attention to the key points.

 

In response to a question from a Member regarding previous plans for Fleet Street, the Director of the Built Environment advised that the project would take account of proposals for other developments in the area. The Director of the Built Environment also confirmed that officers were working with the Climate Action team to ensure that the project was aligned with the Climate Action Strategy.

 

RESOLVED – That the Streets & Walkways Sub Committee:

 

  1. Agree that a budget of £87,200 is approved to reach the next Gateway;

 

  1. Note the total estimated cost of the project at £255,006.20 (excluding risk); and

 

  1. Approve the eastern extension of the Healthy Streets Plan boundary to align with the Fleet Street Partnership area boundary.