Agenda item

Gateway 6 - Outcome Report - London Bridge Waterproofing and Bearings Replacement

Report of the Director of the Built Environment.

Minutes:

The Committee considered a Gateway 6 – Outcome Report of the Director of the Built Environment regarding the London Bridge Waterproofing and Bearings Replacement work.

 

The Committee were informed that the Director of the Built Environment was immensely proud of the team involved in this work for completing the project early by immediately responding to the first national lockdown in March 2020 to find safe ways of working and keep the project running.

 

The Chair added the Committee’s thanks to Officers for completing this high profile wor succesfully.

 

RESOLVED – That the Committee:

·         Approve the closure of the project, providing the final account is agreed within £2,626,000

·         Delegate authority to the Chief Officer to agree a settlement of disputed items, if this becomes necessary,

·         Delegate authority to the Chief Officer to use released but unspent CRP allocation (up to £61,000) to settle, if this becomes necessary.