Report of the Director of the Built Environment.
Minutes:
The Committee considered a Gateway 5 report of the Director of the Built Environment relative to West Smithfield & Charterhouse Street (Thameslink) Bridges Remedial Works.
RESOLVED - That, the Committee:
· Agree the total revised project budget of £645,000 (excluding risk);
· Approve the appointment of Dyer & Butler (incumbent Tunnel Lids contractor) by means of a variation to their currently approved works order in the total value of £390,000;
· Approve a Costed Risk Provision of £150,000 over and above the £645,000 (to be drawn down via delegation to Chief Officer).
Supporting documents: