Gateway 3/4 - Dominant House Footbridge Future Options

Report of the Director of the Built Environment.

Minutes:

The Committee considered a Gateway 3/4 report of the Director of the Built Environment regarding Dominant House Footbridge Future Options.

 

RESOLVED – That the Committee:

1.    Approve Option 2 (concrete and joint repairs)

  1. Approve the revised total estimated cost of the project at £340, 864 (excluding risk)

3.    Approve budget to proceed to the next gateway (£18,000)