Report of the Director of Community & Children's Services.
Minutes:
The Sub Committee considered a report of the Director of Community & Children’s Services regarding fire compartmentation work to meet statutory requirements.
In presenting the report, Officers advised that timelines were dependant on sprinklers and if a hybrid solution was implemented, this could lead to a reduction in the overall project cost.
RESOLVED -
1.
That £101,665 is approved to
cover the remainder of Studio Partington’s design
fees.
2.
That an additional budget of £10,000 is
approved to cover the Communications Consultant’s
fees.
3.
That Additional Costs are added for staff time
(£20,000).
4. That the revised project budget of £2,050,665(excluding risk) be noted.
Supporting documents: