Agenda item

Electric Vehicle Charging (Oral Update)

Minutes:

The Chair of the Working Party advised that the supplier had been facing resourcing issues nationally, which might last for the next 3-4 months. However, Members noted that 30 charging points had been installed; with 20 working and another 30 currently being installed.   Assuming operation at 60%, it was expected that 40 would be working effectively in the next 3-4 weeks, which is more than the number of electric vehicles on the estate.  Members also noted that the new accounting system was much more efficient, but more work was required on the app.