Report of the Executive Director of Environment.
Minutes:
The Committee considered a report of the Executive Director Environment on the Tower Hill Play Area Refurbishment.
RESOLVED- That: -
I. That budget of £16,000 be approved for staff costs and fees and charges, to reach the next Gateway; and
II. That the project budget of £16,000 (excluding risk) be noted; and
III. That the total estimated cost of the project at £195,000(including risk) be noted; and
IV. That a Costed Risk Provision of £16,500 be approved (to be drawn down via delegation to Chief Officer).