Tower Hill Play Area Refurbishment

Report of the Executive Director of Environment.  

Minutes:

The Committee considered a report of the Executive Director Environment on the Tower Hill Play Area Refurbishment.

 

RESOLVED- That: -

     I.        That budget of £16,000 be approved for staff costs and fees and charges, to reach the next Gateway; and  

    II.        That the project budget of £16,000 (excluding risk) be noted; and  

  III.        That the total estimated cost of the project at £195,000(including risk) be noted; and

  IV.        That a Costed Risk Provision of £16,500 be approved (to be drawn down via delegation to Chief Officer).

 