Agenda item

100 Minories Phase Two: Public Realm enhancements

To consider the report of the Director of the Built Environment ‘100 Minories Phase Two: Public Realm enhancements to Crescent’.

 

Minutes:

The Sub-Committee considered the report of the Director of the Built Environment ‘100 Minories Phase Two: Public Realm enhancements to Crescent’.

 

A Member suggested that there was merit in utilising the current developer’s expertise where possible, rather than looking elsewhere.

 

A Member sought clarification on whether there had been a change in developer or whether the change had been in the hotel operator and asked if legal obligations had passed to the developer.

 

Members heard that the Corporation was working with the new owners of the site.

 

RESOLVED, that the Sub-Committee

 

1.    Approve the amended scope of the project to include climate resilience measures and note that a final design and cost estimate will be set out at Gateway 4/5.

2.    Approve the revised funding strategy as set out in this report to include funding from the Cool Streets and Greening Programme in addition to previously allocated S106 funds.

3.   Approve the additional budget of £29,819, funded from the 100 Minories S106for Phase 2 to reach the next gateway.

 

Supporting documents: