To consider the report of the Executive Director Environment.
Minutes:
Resolved, That Members
1. Note and approve the contents of this report;
2. Approve the transfer of the project management, oversight, funding and financial responsibilities of the incomplete works identified in the Crossrail Liverpool Street Phase 1 project (11375) Gateway 6 to this project for completion (detailed in paragraph 4.8);
3. To accommodate the previous recommendation, note and approve a £155,000 increase in the total estimated project cost to approx. £1.64m, as shown in Appendix 2. This funding is to be provided by the Crossrail Liverpool Street Phase 1 project;
4. Note and approve the updated ‘Fees’ budget expenditure description to include feasibility design work by third parties (detailed in paragraph 5.3);
5. Approve the updated costed risk register in Appendix 3, to be drawn down via delegation to Chief Officer. (Overall CRP amount has not changed since last report);
6. Approve the removal of the temporary social distancing measures and associated Temporary Traffic Regulation Order from Old Broad Street between London Wall and Liverpool Street, previously implemented by the Covid-19 On Street Response.