Crossrail Liverpool Street Urban Integration (Phase 2) G3

To consider the report of the Executive Director Environment.

Minutes:

Resolved, That Members

 

1.    Note and approve the contents of this report;

 

2.    Approve the transfer of the project management, oversight, funding and financial responsibilities of the incomplete works identified in the Crossrail Liverpool Street Phase 1 project (11375) Gateway 6 to this project for completion (detailed in paragraph 4.8);

 

3.    To accommodate the previous recommendation, note and approve a £155,000 increase in the total estimated project cost to approx. £1.64m, as shown in Appendix 2. This funding is to be provided by the Crossrail Liverpool Street Phase 1 project;

 

4.    Note and approve the updated ‘Fees’ budget expenditure description to include feasibility design work by third parties (detailed in paragraph 5.3);

 

5.    Approve the updated costed risk register in Appendix 3, to be drawn down via delegation to Chief Officer. (Overall CRP amount has not changed since last report);

 

6.    Approve the removal of the temporary social distancing measures and associated Temporary Traffic Regulation Order from Old Broad Street between London Wall and Liverpool Street, previously implemented by the Covid-19 On Street Response.

 