Report of the Executive Director of Environment
Minutes:
The Sub Committee considered a report of the Executive Director, Environment regarding the resurfacing of Parliament Hill Athletics Track. In response to a question from a Member, the Executive Director, environment confirmed that funding had been agreed in principle by Resource Allocation Sub Committee but was subject to approval for drawdown.
RESOLVED – That the Operational Property and Projects Sub Committee agree:
1. That budget of £81,000 is approved to reach the next Gateway; and
2. That a costed risk provision of £30,000 is approved (to be drawn down via delegation to the Chief Officer) see appendix 2.