Report of the Executive Director of Environment
Minutes:
The Sub Committee considered a Gateway 6 report of the Executive Director, Environment regarding the 60 London Wall S278 highway improvements.
RESOLVED – That the Operational Property and Projects Sub Committee:
i) Approve the content of this outcome report noting that the project was delivered to meet the developers programme and within the budget approved at G5;
ii) Authorise the Chamberlain’s department to return unspent S278 funds to the Developer as set out in the s278 legal agreement (subject to the verification of the final account); and
iii) Agree to close the 60 London Wall project.
Supporting documents: