Agenda item

60 London Wall S278

To consider the report of the Executive Director Environment.

Minutes:

The Committee considered the report of the Executive Director Environment.

 

 

RESOLVED, That the Committee

 

1.    Approve the content of this outcome report noting that the project was delivered to meet the developers programme and within the budget approved at G5.

2.    Authorise the Chamberlain’s department to return unspent S278 funds to the Developer as set out in the s278 legal agreement (subject to the verification of the final account); and

3.    Agree to close the 60 London Wall project.

 