To consider the report of the Executive Director, Environment.
Minutes:
The Sub-Committee considered the report of the Executive Director, Environment.
A Member asked whether SuDS measures would be used for the Moor Lane project, and the meeting heard that sustainable drainage was expecting to be incorporated into that design, though there had been some constraints around that.
The meeting noted that the use of permeable paving was an opportunity to align with the Sports Strategy.
RESOLVED, That the Sub-Committee
1. Approve Option 2 to include SuDS measures in strategically located sites, noting the locations of the proposed sites; and
2. Approve the budget of £185,000 for design and monitoring infrastructure for Phase 4 SuDS for Climate resilience to reach Gateway 4.
Supporting documents: