The Sub Committee considered a report
from the Director of Community and Child Services regarding the
GW3: West Smithfield Public Realm and Transport.
RESOLVED – that the
Sub-Committee:
approved the additional budget of
£54,225 to reach Gateway 6 of which £48,010 is
associated with the variation for AD Construction (works) and
£6,215 for the extension of time for Contract Administration
duties undertaken by Playle and
Partners (fees).
note the new total estimated cost of
the project at £1,659,146.