Report of the Interim Executive Director, Environment.
Minutes:
The Sub-Committee considered a report of the Interim Executive Director, Environment concerning public realm improvements related to the redevelopment of Dauntsey House, 4A & 4B Frederick’s Place, to improve pedestrian movement.
RESOLVED – That Members of the Sub-Committee
1. Approve the budget of £25,000 for Evaluation and Design to reach the next Gateway;
2. Note the total estimated cost of the project £350,000 - £600,000 (excluding risk), funded from the Section 106 and Section 278; and
3. Grant permission to enter into a Section 278 Agreement in accordance with the completed Section 106 Deed of Agreement related to the redevelopment of Dauntsey House, 4A & 4B Frederick’s Place.