The Sub-Committee received a report of the
Director, Community & Children’s Services providing an
update to Members on the progress that has been made with the
Housing Major Works Programme and to advise Members on issues
affecting progress on individual schemes.
The following points were noted:
- Programme Overview: It was noted that
the current major works programme was valued at £110 million,
covering works completed and those in progress. This did not
include future works, which are estimated at £30
million.
- Governance: Members noted that there was a need for robust
governance on major projects, similar to the approach used for the
Middlesex Street project, to ensure effective management and
communication.
- Acceleration of Programme: Discussions
included the possibility of accelerating priority issues within the
programme, considering financial support and capacity to move
projects forward more quickly.
- Net Zero Considerations: Officers
informed Members the programme included considerations for
achieving net zero, with support from the City of London
Corporation's Climate Action Strategy team.
- Golden Lane Project: Emphasis on the
importance of governance for the Golden Lane project, with plans to
implement a governance structure in November was
expressed.