Housing Major Works Programme – Progress Report

Report of the Director of Community & Children’s Services.

Minutes:

The Sub-Committee received a report of the Director of Community & Children’s Services concerning update Members on the progress that has been made with development of the Housing Major Works Programme following September’s HRA briefing session and to advise Members on issues affecting progress on individual schemes.

 

The following points were noted:

 

  • Window Replacement Projects: Officers provided updates on various window replacement projects. Holloway Estate, Sydenham Hill, and Windsor House have achieved practical completion. William Blake was in the design phase, with an updated program expected soon.
  • Middlesex Street Heating: The project is expected to complete by April 2025, pending the outcome of a tribunal in December.
  • Fire Door Programme: Progress on the fire door programme was discussed, with specific updates on different lots. Avondale Square is complete, and work is ongoing at Sumner House, William Blake, Dron House, and Petticoat Tower.
  • Golden Lane Estate: Concerns were raised about the timeline, costs, and scope of works, including the need to address common parts and decanting plans. The Deputy Chairman emphasised the need for a detailed plan and clear communication with residents.
  • General Concerns: Members expressed concerns about project delays, costs, and the need for better planning and communication with residents. Officers acknowledged these issues and committed to providing more detailed updates and plans in future meetings.

 