The Sub-Committee received a report of the
Director of Community & Children’s Services concerning
update Members on the progress that has been made with development
of the Housing Major Works Programme following September’s
HRA briefing session and to advise Members on issues affecting
progress on individual schemes.
The following points were noted:
- Window Replacement Projects:
Officers provided updates on various window replacement projects.
Holloway Estate, Sydenham Hill, and Windsor House have achieved
practical completion. William Blake was in the design phase, with
an updated program expected soon.
- Middlesex Street Heating: The
project is expected to complete by April 2025, pending the outcome
of a tribunal in December.
- Fire Door Programme: Progress
on the fire door programme was discussed, with specific updates on
different lots. Avondale Square is complete, and work is ongoing at
Sumner House, William Blake, Dron House, and Petticoat Tower.
- Golden Lane Estate: Concerns
were raised about the timeline, costs, and scope of works,
including the need to address common parts and decanting plans. The
Deputy Chairman emphasised the need for a detailed plan and clear
communication with residents.
- General Concerns: Members
expressed concerns about project delays, costs, and the need for
better planning and communication with residents. Officers
acknowledged these issues and committed to providing more detailed
updates and plans in future meetings.