Minutes:
There were several questions raised by Members.
· What has caused the further delays to the Crescent House Windows replacement project?
The delays are due to bio-safety issues and the inclusion of external works that were not part of the original programme.
· Why weren't residents informed about the delays?
The project team had a meeting in November with members of the Crescent House CSG to explain the issues and promised to provide an overarching programme by the end of January.
· What impacts will the delays have on the wider estate?
The delays have caused significant frustration among residents, particularly leaseholders, due to the increasing costs of the works.
· Who will bear the costs of the works?
There are ongoing discussions about who will bear the costs. Partial advice has been received from the legal team, and further advice is being sought regarding the heating issue and the improvement versus repairs issue.
· What is the scope of the project?
The project scope includes not just window replacements but also other pressing works such as electrics, fire doors, and concrete repairs.
· What are the plans for future meetings with residents?
The team is planning future meetings with residents and will send out a letter with more information shortly.