Agenda item

Issue Report (With Change Request) - Fire Safety Planned Maintenance Programme 2028-31

Report of the Executive Director, Community and Children’s Services.

Minutes:

The Committee received the report of the Executive Director, Community and Children’s Services. Officers explained that the report related to essential fire safety works required to all the residential housing estates and the additional expenditure requested was for critical surveys, exploratory works and investigations to inform the development of the programme. The multi-disciplinary consultant undertook a gap analysis of fire safety related documents, that revealed the absence of documents such as fire strategies.

 

A Member asked whether it was separate to the ongoing major works projects, as those included some fire safety work. Officers explained that it was part of the Housing Major Works Programme and was specific to fire safety related work across the portfolio. There was fire safety work included in Golden Lane Estate packages, elsewhere that was not the case. There was an uplift requested of £450,000 from within the £211 million budget.

 

The Deputy Chair sought assurance from officers that going forward they would do all they could to work within the existing envelope and not seek additional money. Officers explained that being at the outset for design development there was potential for costs to increase, however cost consultants were in place to manage that; there was contingency in the programme.

 

A Member referred to the RAG rating and asked whether the risk status was in relation to the programme or the risk of actual fires. Officers explained that it concerned project related risks, regarding overspend or programme extension.

 

A Member welcomed the additional funding for surveys as a lack of information had formed a lot of the work the housing team had been doing to fix the problems over many years. The Member noted that it would be good to think about when those surveys might need to be redone, building those costs in the budget going forward. The Member presumed that the new staff being recruited regarding the specialist regulatory knowledge would be in a position going forward to know the liability and ensure the works were up to standard. Officers explained that work was underway with colleagues from health and safety.

 

A Member queried when the missing documentation would be supplied as a matter of high priority. The Member asked what the Clerk of Works would oversee and when the role would be filled. Officers explained that the survey programme was scheduled for completion by October 2026. The Clerk of Works role would be filled in-house during the delivery phase, supported by external consultancy as the programme develops.

 

RESOLVED:

1.          Approved an additional fees budget of £1,250,000 for preliminary surveys, Fire Strategies, reports and exploratory works.

2.          Noted the revised total project budget of £12,450,000 (excluding risk).

3.          Noted that this represents an uplift of £450,000 in the total fees, surveys and exploratory works budget from the Gateway 1 Report of May 2026.

 

Supporting documents: