City of London Freemen’s School – Masterplan Phase 1

 

We report for information action taken under Standing Order No. 19 approving additional expenditure in relation to phase 1 of the City of London Freemen’s School(CLFS) masterplan project works.

 

The CLFS masterplan project phase 1 works are 50% complete. A number of issues have arisen with this phase of the project which require additional building works. The total cost needed to progress the project amounts to £240,000, payable from the CLFS reserves. In addition, the project submission for phase 2 will not be considered until phase 1 is substantially complete so that the scope of the works can be more clearly identified.

 

It was necessary to use urgency procedures to approve these works to ensure that the completion of phase 1 does not result in long delays to the overall project.

 

Minutes:

BOARD OF GOVERNORS OF THE CITY OF LONDON FREEMEN'S SCHOOL

(Stuart John Fraser, CBE)

27 June 2013

City of London Freemen’s School – Masterplan Phase 1

We report for information action taken under Standing Order No. 19 approving additional expenditure in relation to phase 1 of the City of London Freemen’s School(CLFS) masterplan project works.

 

The CLFS masterplan project phase 1 works are 50% complete. A number of issues have arisen with this phase of the project which require additional building works. The total cost needed to progress the project amounts to £240,000, payable from the CLFS reserves. In addition, the project submission for phase 2 will not be considered until phase 1 is substantially complete so that the scope of the works can be more clearly identified.

 

It was necessary to use urgency procedures to approve these works to ensure that the completion of phase 1 does not result in long delays to the overall project.

 

Read and agreed to.