Minutes:
A report of the Director of the Built Environment was considered relative to 5 Broadgate.
Following a brief discussion the sub-committee requested that consideration be given to seeking a longer period of funding from Section 106/278 arrangement(s), perhaps as long as 20 years, for the maintenance of street scene features.
RESOLVED – That,
i) the design as detailed in the main body of the report and in Appendix 1be approved;
ii) the budget and associated tolerances as set out in the main body of the report be approved;
iii) the commencement of the project in line with the outline programme as detailed in section 15 of this report be approved;
iv) the Director of the Built Environment be authorised to agree arrangements for the land shown in Appendix 3 to be dedicated and accepted as public highway and to instruct the Comptroller & City Solicitor to complete any necessary deeds; and
v) The Director of the Built Environment be requested to seek from the developer a longer period of funding from Section 106/278 arrangement(s) for the maintenance of street scene features.