Internal Audit Update report

Report of the Head of Internal Audit and Risk Management.

Minutes:

The Sub Committee considered a report of the Head of Internal Audit and Risk Management which provided an update on the internal audit reviews undertaken between May 2014 and August 2014.

 

Assurance Mapping – The Head of Internal Audit agreed to discuss the matter of Assurance Mapping with the City of London Police to identify gaps in assurance to inform future internal audit work.

 

Further details would be circulated in relation to police compensation claims, i.e. numbers, costs and trends, as part of the next audit update to the next meeting on 19 November 2014.

 

The Sub Committee discussed the revised completion dates for 2013/14 work and it was agreed to provide a progress report on the outstanding reviews, once completed.

 

It was noted that the delivery of the 2014/15 audit programme would be provided within the specified timescales.

 

It was noted that confirmation of resources, delivery plans and completion dates for the 2014/15 audit programme would be provided at the next meeting on 19 November 2014 within the internal audit update report.

 

RESOLVED – That the report be noted.